Site 7 Auckland International Airport

Construction

Industrial

6 Percival Gull Place, Airport

Auckland International Airport Ltd

$8.0 million

7 months

Architects /
Eclipse Architecture  

Engineers /
Day Consultants  

Client Project Manager /
RDT Pacific 

This project included a relatively complex warehouse and 6 separate office pods. Early challenges involved remediating ground conditions where extensive undercuts were required, and later on the multiple fitouts requiring careful planning.

 The building was un-tenanted at the time of construction, so a very high quality product was required to attract tenants. Despite the hurdles the site team were able to deliver, resulting in a delighted client. Another key delivery area for the client was the Health and Safety standards expected on site, which were set above the industry norm. Haydn and Rollett were able to meet these standards and the commitment to the safety was highlighted in the statistics, approximately  42,000 man hours were worked and with no lost time injuries.

8,000m² Warehouse
1,800m² of Canopies
820m² of Offices
Yards and carparking to the balance of the 4,350m² site